ABU DHABI PROJECTS
Upper Zakum UZ 750 Island Surface Facilities – EPC 2
CLIENT
ZADCO
CONSULTANT
Petrofac International Ltd
CONTRACT VALUE
AED 808.7 Million
DURATION
September 2014 to August 2017
LOCATION
Upper Zakum 750 Islands – Abu Dhabi
THE CHALLENGE
The Upper Zakum Oil Field is the largest producing field in ADNOC's portfolio. It is also the second-largest offshore oil field and the fourth-largest oil field in the world. The UZ750 project involved the construction of four artificial islands, comprising a central complex housing the processing facilities as well as the north, south and west satellite platforms.
SCOPE OF WORK
- 001Civil works for Central and West Islands involves settlement monitoring of critical foundations.
- 002Filing and Grading, Excavation for Foundations and backfilling.
- 003Road Works.
- 004RCC Drain Lines for Storm Water.
- 005Landscaping.
- 006Demolition Works.
- 007Building Package – RCC Bldgs. (CNIA & Utility Electric Substation).
- 008Piling Works and related works such as Geotechnical & Structural Design of Piles.
- 009Construction of SWI Structures and Outfall Structure.