
YAS Island Development – Multiple Infrastructure Contracts
Aldar Properties
Halcrow International Partnership
AED 1.9 Billion
October 2007 to May 2010
Yas Island – Emirates of Abu Dhabi
As the island was preparing for the first ever Formula One race in Abu Dhabi, NBHH was proudly staking a claim as the group that made it possible for spectators to reach the circuit, and experience the event first hand; Basically, the road networks within the complex and the infrastructure that supports it have been constructed by our group. In that latter event alone, NBHH has contracted and achieved six infrastructure contracts as follows: - Package 2B, the main infrastructure works contract - Formula One gateway park, infrastructure and landscaping package - Underground potable water tank - Retail Mall phase 1A, roads and infrastructure works - Ferrari World theme park and environs, roads and utilities works - Marina area, hard and soft landscaping, roads and infrastructure works 920 staff members and construction workers have participated to the successful completion of this project and to its timely handover. The project team managed all the different road blocks and challenges, delivering the works on schedule, while accommodating design changes and
- 001Roads network: 12 km of dual carriage ways
- 002Underpass: 250 m length
- 003Pumping station for the underpass
- 004Street lighting: 10 m and 14 m decorative streetlights plus cabling
- 005Irrigation: 150 mm to 900 mm pipes: 15 km
- 006Potable water: 150 mm to 900 mm pipes: 25 km
- 007Stormwater: 300 mm to 2200 mm pipes: 14 km
- 008Sewerage: 300 mm to 1200 mm pipes: 12 km
- 009Telecom cabling: 220 km
- 010Gas pipes: 10 km
- 011Car parking: 60,000 m2
- 012Landscaping and grass: 300,000 m2
- 013Underground potable water reservoir: 135,000 m3
- 014Shoring and dewatering for deep excavations
- 015Piling: 300 piles of various diameters and depth
- 016Setting up of asphalt plant: production of 230 000 tons of asphalt

Al Nahda Infrastructure Works and Streetscape Package 1 & 2
ALDAR
AECOM
AED 1.81 Billion
June 09, 2025 to December 09, 2027
Abu Dhabi
The Al Nahda Infrastructure Project is a major, large-scale infrastructure development in Abu Dhabi, United Arab Emirates, involving the design and build of extensive infrastructure networks and streetscape works to support future urban development. The project encompasses comprehensive wet and dry utility networks, including sewerage, stormwater drainage, potable water, irrigation, electrical power distribution, telecommunications, substations, and pumping stations, together with extensive road networks, landscaping, and public realm infrastructure. The scale and complexity of this development require integrated engineering solutions, comprehensive planning, multidisciplinary design coordination, and phased construction to ensure the successful delivery of essential infrastructure for a modern, sustainable urban community.
- 001Sewerage & Stormwater Networks – Construction of 74 km of sewer pipelines with 1,536 manholes, 17 km of sewer house connections, and 159 km of stormwater drainage pipelines, including 1,153 stormwater manholes and 3,890 inlet chambers.
- 002Water Supply & Irrigation Networks – Installation of 106 km of potable water pipelines and 93 km of irrigation pipelines, including associated valve chambers, hydrants, fittings, and recycled water infrastructure.
- 003Stormwater & Irrigation Pumping Stations – Design and construction of two stormwater pumping stations and one irrigation pumping station, including associated civil, mechanical, electrical, and control systems.
- 004Electrical Power, MCC & Street Lighting – Installation of 158 km of MV cables, 166 km of LV cables, and 131 km of street lighting cables, including 2,904 street lighting poles, electrical substations, MCC infrastructure, duct banks, and associated power distribution systems.
- 005Telecommunications & Traffic Systems – Installation of 205 km of telecommunications cables, including 1,321 telecom chambers, fiber-optic infrastructure, and associated traffic signal systems.
- 006Earthworks & Road Infrastructure – Construction of around 100 km of main and internal road networks, including site grading, excavation, backfilling and compaction, asphalt paving, kerbstones, pedestrian pathways, and traffic signage.
- 007Landscaping & Public Realm Works – Development of soft and hard landscaping, pedestrian and cycling facilities, street furniture, and associated public realm infrastructure.

Upper Zakum UZ 750 Island Surface Facilities – EPC 2
ZADCO
Petrofac International Ltd
AED 808.7 Million
September 2014 to August 2017
Upper Zakum 750 Islands – Abu Dhabi
The Upper Zakum Oil Field is the largest producing field in ADNOC's portfolio. It is also the second-largest offshore oil field and the fourth-largest oil field in the world. The UZ750 project involved the construction of four artificial islands, comprising a central complex housing the processing facilities as well as the north, south and west satellite platforms.
- 001Civil works for Central and West Islands involves settlement monitoring of critical foundations.
- 002Filing and Grading, Excavation for Foundations and backfilling.
- 003Road Works.
- 004RCC Drain Lines for Storm Water.
- 005Landscaping.
- 006Demolition Works.
- 007Building Package – RCC Bldgs. (CNIA & Utility Electric Substation).
- 008Piling Works and related works such as Geotechnical & Structural Design of Piles.
- 009Construction of SWI Structures and Outfall Structure.

Riyadh City North – Phase 7 B Infrastructure and Streetscape
Aldar
Parsons International
AED 669 Million
November 2021 to November 2023
Abu Dhabi
The object of the project is the construction of roads and infrastructure works for Phase 7 of Riyadh City North, Abu Dhabi. The works will include the construction of internal and external roads, lighting, potable water network, rainwater drainage systems, sewerage systems, fire-fighting systems, traffic control systems, irrigation networks, electricity grids, and Public Utilities.
- 001Site Clearance
- 002Sewer network (Line-19,818m, Manhole-142No's)
- 003Storm water works (Line – 19415m, Inlet/catch basin- 2998 No's, discharge pond)
- 004Road Works: – (Excavation – 584,950m3, Fill – 367,700m3, Subbase – 225,965 m3 Asphalt – 12,651 ton, Tiles – 833,830m2, Kerbstone – 472,720m)
- 005Street lighting works (Cables = 121,605m, Poles – 2383 No's)
- 006Electrical works (Cables – 737,324m, feeder pillar- 561No's, 22/0.4kv Distribution Substation – 76No's)
- 007Water works (Line – 25,796m, Valve chambers-216 No's, Fire hydrant – 164 No's, house connections,)
- 008Gas Works – (Line – 313,622m, valves – 7348 No's)
- 009Telecommunication works (JRC's – 206 No's, Ducts – 38,284m)
- 010Irrigation Works (Line 440,250m, Valves – 381 No's, pumping station – 2 No's)
- 011Landscaping Works (Hard & Soft landscaping works)
- 012Falcon Eye Network (Conduits – 225,382m)

Yas Canal Community Package 02 – Primary Roads & Infrastructure
ICT RED
DAR
AED 637.04 Million
May 01, 2026 to May 10, 2028
Abu Dhabi
The project involves the design of infrastructure system and streetscape within YAS Canal Community, which is located south of Yas Island along the Yas Canal. The main land-uses include residential (i.e. residential villas), commercial, mixed use commercial, schools and community facilities. YAS Canal Community covers a total area of about 418 Hectares. The entire site is currently fenced and is comprised of largely undeveloped land. The site is currently empty with clusters of abandoned farms/plantations.
- 001Construction of Utilities like Sewer, Storm water, Potable Water, Irrigation, Recycled Water, Telecom, MCC, Gas; Storm Water Pump Station, Potable Water Reservoir and Pumping Station, Recycle Water Reservoir and Pumping Station, Electrical Network, Sub station, Traffic Control System and Road works.

Riyadh City South – Phase 2 Infrastructure & Streetscape
Modon Properties
ARCADIS
AED 564.7 Million
March 2020 to May 2022
Abu Dhabi
The Project includes for the construction for the infrastructure works and public realm to the the ROW for the Phase 2 development area. The total Site area for the project is 8,890,483.00 m2.
- 001Sewer Network is almost 86 km of uPVC & GRP pipes
- 002Storm Water Network is almost 104 km of GRP pipes
- 003Construction of approximately 112,559 m of HDPE potable water networks
- 004Irrigation network within Phase 2 is approximately 78,756 m
- 005Street lighting control cabinets and distribution boards
- 006Gas distribution network
- 007Construction of roadways consists of approximately 744,000 m2
- 008Power Works
- 009Telecommunication Networks
- 010Public Realm Works
- 011Landscape (hard and soft)
- 012Drainage Networks
- 013Signage & Wayfinding etc

Saadiyat Beach Apartment
Nael & Bin Harmal Hydroexport
Dorsch Gruppe
AED 501 Million
October 2015 to October 2020
Abu Dhabi
The Saadiyat Beach Apartments project is located on Saadiyat Island, an island just to the north of the city of Abu Dhabi. Saadiyat will be a master planned community of approximately 150,000 residents and will offer island users a range of housing, employment, retail, entertainment and outdoor parks and natural preservation areas. The project site is a Greenfield development located on the land parcels SB-21. The site land use is assigned as residential and the total GFA of approximately 77,037 m2.
- 001The project comprises three developments featuring high quality 5 residential apartments of G+4 and G+5 (Premium Buildings) with basement and associated communal facilities buildings, parks and ancillary services buildings.

EPC for ASAB Full Field Development Project
Abu Dhabi Company for Onshore Oil Operation (ADCO)
Petrofac International Ltd
AED 290 Million
September 2009 to September 2013
Western Region – Abu Dhabi
The project is located in the western region of Abu Dhabi, and is part of the oil and gas field of ASAB. Petrofac has awarded the contract to NBHH in 2008 for a contract duration of 44 months. Given the location of the project, in the middle of the desert, and taking into account the requirements and constraints related to working with the oil and gas industry, the logistics became a critical aspect of the works and the strict implementation of all safety, quality and environmental procedures became a must. Over 1000 staff from NBHH were trained to work in this environment, and were an integral part of this challenging achievement.
- 001Construction of RCC buildings for sub stations at various locations
- 002Construction of central control building with specialized finishes
- 003Service buildings and gate house including all the MEP services in highly sensitive oil field area, designated as hazardous area, where the stringent control of safety and quality procedures is exercised by the client
- 004Asphalt road works, gulch road as well as fixing of Kerbstone and Interlock paving
- 005Installation of concrete batching plant
