NBHH logo
Back
PROJECT CATEGORY

DUBAI
PROJECTS.

DS – 429: Sewerage and Stormwater Drainage Systems for Industrial Communities  (128, 215, 242, 612, 613)
DUBAI PROJECTS

DS – 429: Sewerage and Stormwater Drainage Systems for Industrial Communities (128, 215, 242, 612, 613)

CLIENT

Dubai Municipality

CONSULTANT

Stantec

CONTRACT VALUE

AED 706.91 Million

DURATION

December 24, 2024 to September 08, 2028

LOCATION

Dubai

THE CHALLENGE

Live roads - Maintain traffic flow and property access during pipeline installation. Groundwater - Manage groundwater inflows to keep trenches and NDRC pits stable. Nearby buildings and structures - Limit vibration and ground movement during construction. Existing utilities - Verify utility locations and protect services during the works.

SCOPE OF WORK
  • 001Construct a sewer network in Al Khabaisi and Umm Ramool with 32.44 km of main sewer lines, comprising 24.18 km by open-cut excavation and 8.26 km by Non-Disruptive Road Crossing (NDRC). Include associated manholes as part of the pipeline works.
  • 002Construct a stormwater drainage network in Al Khabaisi with 44.62 km of main stormwater lines, comprising 25.34 km by open-cut excavation and 19.28 km by NDRC. Include associated manholes as part of the pipeline works.
  • 003Install house connection lines to connect individual properties and industrial units to the main sewer network.
  • 004Install catch basins and gully connections to collect and convey surface runoff to the stormwater network. Install land drains for subsurface drainage.
  • 005Construct a stormwater pumping station and provide an oil separator and an outfall for stormwater discharge.
DS-204/C1 Connecting Developed Communities in Dubai Land to DM Sewerage System
DUBAI PROJECTS

DS-204/C1 Connecting Developed Communities in Dubai Land to DM Sewerage System

CLIENT

Dubai Municipality

CONSULTANT

Khatib & Alami

CONTRACT VALUE

AED 479 Million

DURATION

August 03, 2026 to January 18, 2029

LOCATION

Dubai

THE CHALLENGE

Live roads - Maintain traffic flow and property access during pipeline installation. Ongoing projects - Coordinate work areas, access, and construction sequencing with other contractors. Existing services - Verify utility locations and protect existing services during excavation and NDRC works.

SCOPE OF WORK
  • 001Construct 9.67 km of sewerage pipelines, including 2.30 km by open-cut excavation with 12 manholes and 7.37 km by Non-Disruptive Road Crossing (NDRC) with 56 manholes.
  • 002Construct 18.10 km of stormwater drainage pipelines, including 7.63 km by open-cut excavation with 39 manholes and 10.47 km by NDRC with 69 manholes.
  • 003Install 2.90 km of gully and catch basin connection pipelines, including 140 gullies and catch basins in total.
  • 004Construct one sewage pumping station, including civil, mechanical, electrical, and associated works.
  • 005Install approximately 838 m of pressure pipeline associated with the sewage pumping station.
  • 006Construct approximately 2.73 km of drainage channels.
Dubai Metro – Utilities Diversion, Protection and Relocation
DUBAI PROJECTS

Dubai Metro – Utilities Diversion, Protection and Relocation

CLIENT

RTA

CONSULTANT

Systra / Parsons

CONTRACT VALUE

AED 412 Million

DURATION

December 2005 to August 2009

LOCATION

Dubai

THE CHALLENGE

Every infrastructure project planned in the middle of an active city is poised to encounter and mitigate various risks, mostly in relation to existing underground utilities. The Dubai Metro project was not an exception. The detection, protection and eventually the diversion of existing utilities was a challenging and critical task for NBHH especially where the underground metro stations, cut and cover tunnels, or piling foundations had to be constructed. The latter construction activities had to be carried out while minimizing the disturbance to the end users and Dubai residents. In that respect, our company managed to overcome all the different challenges, whether foreseen or unforeseen, for a project duration that spanned for three and half years.

SCOPE OF WORK
  • 001Obtaining No Objection Certificates (NOC) from the relevant government departments
  • 002Preparation of shop drawings and method statements
  • 003Trial pits, often by hand digging for initial identification and inspection
  • 004Temporary works such as shoring for deep excavation, dewatering, saw cutting of asphalt
  • 005Reinstatement of roads and pavements
  • 006Supply of all materials and provision of all necessary equipment
  • 007Relocation and protection of existing underground pipes of diameters from 100 mm to 1400 mm for various kind of utilities such as water, sewerage, stormwater drainage, irrigation etc… Including construction of manholes, chambers and connection to existing networks
  • 008Relocation and protection of existing underground cables and ducts for electricity (ADWEA) and telecommunication (Etisalat)
  • 009Micro tunneling and directional drilling for underground crossings and the installation of cables, ducts and pipes
DS – 288: Interconnecting Urgent Development to DM Sewerage System-Deira Area
DUBAI PROJECTS

DS – 288: Interconnecting Urgent Development to DM Sewerage System-Deira Area

CLIENT

Dubai Municipality

CONSULTANT

ITAL Consult

CONTRACT VALUE

AED 349.85 Million

DURATION

February 19, 2025 to August 08, 2027

LOCATION

Dubai

THE CHALLENGE

Tender covers the construction of sewerage systems strengthen the existing sewerage network by providing adequately sized Link sewer connections to these existing sewerage network, decommissioning of subsidiary pumping station including main Pumping station, providing sewerage connections to the new developments and/or un-served areas; conveying the generated wastewater to the existing functional system; provisions of future connections from another deep link sewer and with future sewage tunnel(s). Lifting Pump Station with a capacity of 700 L/s is proposed at terminal point, of deep link sewer.

SCOPE OF WORK
  • 001Site clearance
  • 002Construction of the following link sewer pipelines by Non-Disruptive Methods (NDM) for 600, 700, 800, 900, 1000, 1500, and 2500mm Dia pipes and associated manholes with total length 12181.35 meters, 67 NDM Pits and manholes
  • 003Construction of open cut Sewerage Works includes Pipeline, Manhole Construction & House Connection Pipeline & Chamber works (pipe line 3,704-meter, House connection 3,906 meter and manholes 62 Nos)
  • 004Construction works of new sewage lifting pump station
  • 005Construct Stub-out Pipes for future connections, Manholes
  • 006Abandonment/ Demolition of Existing Subsidiary Pumping Stations
DS 306/1: Stormwater Drainage System in Jebel Ali and Developers Areas–Phase 1
DUBAI PROJECTS

DS 306/1: Stormwater Drainage System in Jebel Ali and Developers Areas–Phase 1

CLIENT

Dubai Municipality

CONSULTANT

Stantec

CONTRACT VALUE

AED 265.38 Million

DURATION

January 14, 2025 to January 15, 2027

LOCATION

Dubai

THE CHALLENGE

Ongoing road projects - Coordinate work with the ongoing road project to execute the works. Existing Etihad Rail crossing - Etihad Rail Crossing by NDRC. Existing bridges - Works close to the foundations of Existing Bridges. Limited groundwater discharge points - Manage dewatering with insufficient discharge points for the pumped groundwater.

SCOPE OF WORK
  • 001Construct 11,110 m of stormwater trunk line, including 1,193 m by open-cut excavation and 9,917 m by Non-Disruptive Road Crossing (NDRC). The works include excavating 46 pits and constructing 52 manholes.
  • 002Construct drainage ditches as part of the stormwater drainage system.
  • 003Construct a stormwater lifting station.
Grand Cosmopolitan Hotel
DUBAI PROJECTS

Grand Cosmopolitan Hotel

CLIENT

Nael Bin Harmal

CONSULTANT

EDMAC Consultant

CONTRACT VALUE

AED 210 Million

DURATION

October 2014 to October 2018

LOCATION

Dubai

THE CHALLENGE

Proposed 2 b + g + m + 6 roof building, Construction of 5 star hotel having 236 rooms which includes suit rooms, rest rooms, handicapped rooms and normal rooms along with Spa, Swimming pools, Ladies amenities, and all relevant construction including MEP works and Fitting out works.

SCOPE OF WORK
    DUBAI PROJECTS

    DS-240/ Part A - House Connection and Miscellaneous Works (Deira & Hatta)

    CLIENT

    Dubai Municipality

    CONSULTANT

    Stantec

    CONTRACT VALUE

    AED 186 Million

    DURATION

    April 08, 2025 to April 07, 2027

    LOCATION

    Dubai

    THE CHALLENGE

    Live roads - Maintain traffic flow and property access during pipeline installation. Logistics - Coordinate crews, equipment, and materials across work locations throughout Dubai, from Deira to Hatta. Authority coordination - Coordinate with the relevant authorities to obtain the required no-objection certificates (NOCs) and permits for thousands of work orders.

    SCOPE OF WORK
    • 001Construct sewerage and stormwater drainage networks, including associated sewer house connections.
    • 002Install approximately 34.29 km of gravity pipelines for the sewerage and stormwater drainage networks.
    • 003Install 11.45 km of HDPE pipelines, including associated chamber works and horizontal directional drilling (HDD).
    • 004Install 3.60 km of pipelines using Non-Disruptive Road Crossing (NDRC) methods.
    • 005Construct 303 manholes and 1,282 chambers for the sewerage and stormwater drainage networks.
    • 006Upgrade the existing pump station.
    • 007Carry out emergency works on irrigation, sewerage, and stormwater pipelines and pump stations.
    DAMAC Islands, Dubai – UAE Deep Services Package
    DUBAI PROJECTS

    DAMAC Islands, Dubai – UAE Deep Services Package

    CLIENT

    Damac

    CONSULTANT

    Khatib Alami

    CONTRACT VALUE

    AED 174.48 Million

    DURATION

    December 03, 2025 to November 22, 2027

    LOCATION

    Dubai

    THE CHALLENGE

    Project covers the construction, completion, testing commissioning and maintenance of the Deep Service Package of Damac Islands approx. 279.33ha with Sewerage, Combined Storm & Groundwater Networks with utility connections to External Existing Networks.

    SCOPE OF WORK
    • 001Construction of Sewerage Works includes Pipeline , Manhole Construction
    • 002Construction of Storm Water System Pipeline, Manhole Construction & Land drain
    • 003Construction of Groundwater Pipeline , Manhole Construction
    • 004Construction of Lifting Stations, Oil Interceptors and Out Fall Chambers
    • 005Construction of Road/Utility crossing by non-disruptive methods
    Design & Construction of TSE Pump Station in the Logistics District of Dubai South
    DUBAI PROJECTS

    Design & Construction of TSE Pump Station in the Logistics District of Dubai South

    CLIENT

    Dubai South

    CONSULTANT

    KEO

    CONTRACT VALUE

    AED 170.73 Million

    DURATION

    December 15, 2025 to August 14, 2027

    LOCATION

    Dubai

    THE CHALLENGE

    This project 276/SE/25 Design and Construction of TSE Pump Station in the Logistics District of Dubai South has been initiated by Dubai South for the Design and Construction of TSE Pump Station along with supply and discharge lines for the pumping station within Dubai South area, a 145 sq.km development centered on Al Maktoum International Airport, in south of Dubai, UAE

    SCOPE OF WORK
    • 0011800 Dia Supply Line (8742 Lm) Including 05 Air Valve, 05 Wash Valve Chamber, 01 Proposed Valve Chamber, 01 Flow Control Valve Chamber, 01 Future Connection Chamber
    • 0021200 Dia Discharge Line (7152 Lm), including 04 Air Valve, 04 Wash Valve Chamber, 1 Proposed Valve Chamber, 07 Future Connection Chamber
    • 003The Design & Build scope includes the complete design, supply, installation, testing, and commissioning of a TSE Pump Station with a capacity of 50,000 m³/day, a 20,000 m³ storage tank, and approximately 9 km supply and 7 km discharge GRP pipelines of DN 1,200 mm. The works cover all civil, mechanical, electrical, MEP, piping, pumping systems, controls, instrumentation, SCADA with remote connectivity, transformers as per DEWA requirements, and associated approvals, in compliance with Dubai Municipality and relevant sewerage authorities
    THE FOUNDATION

    Committed to excellence in every kilometer, every structure.

    Nael & Bin Harmal Hydroexport — architect of the UAE's evolving horizon since 1991.

    ABU DHABI

    Phone : +971 2 6273344
    Fax no. : +971 2 6271165
    Location : 6th Floor, Unit 601, Nael & Bin Harmal (NBH) Tower, Zayed The First St. Al Khalidiyah, Abu Dhabi UAE
    PO Box : 28102

    DUBAI

    Phone : +971 4 3599940
    Fax no. : +971 4 3599941
    Location : 206, Building No: 6 Bay Square, Business Bay, Dubai UAE
    PO Box : 29703

    © 2026 Nael & Bin Harmal Hydroexport LLC. All rights reserved.