Dubai Metro – Utilities Diversion, Protection and Relocation
RTA
Systra / Parsons
AED 412 Million
December 2005 to August 2009
Dubai
Every infrastructure project planned in the middle of an active city is poised to encounter and mitigate various risks, mostly in relation to existing underground utilities. The Dubai Metro project was not an exception. The detection, protection and eventually the diversion of existing utilities was a challenging and critical task for NBHH especially where the underground metro stations, cut and cover tunnels, or piling foundations had to be constructed. The latter construction activities had to be carried out while minimizing the disturbance to the end users and Dubai residents. In that respect, our company managed to overcome all the different challenges, whether foreseen or unforeseen, for a project duration that spanned for three and half years.
- 001Obtaining No Objection Certificates (NOC) from the relevant government departments
- 002Preparation of shop drawings and method statements
- 003Trial pits, often by hand digging for initial identification and inspection
- 004Temporary works such as shoring for deep excavation, dewatering, saw cutting of asphalt
- 005Reinstatement of roads and pavements
- 006Supply of all materials and provision of all necessary equipment
- 007Relocation and protection of existing underground pipes of diameters from 100 mm to 1400 mm for various kind of utilities such as water, sewerage, stormwater drainage, irrigation etc… Including construction of manholes, chambers and connection to existing networks
- 008Relocation and protection of existing underground cables and ducts for electricity (ADWEA) and telecommunication (Etisalat)
- 009Micro tunneling and directional drilling for underground crossings and the installation of cables, ducts and pipes