NBHH logo
Back
Dubai Metro – Utilities Diversion, Protection and Relocation
DUBAI PROJECTS

Dubai Metro – Utilities Diversion, Protection and Relocation

CLIENT

RTA

CONSULTANT

Systra / Parsons

CONTRACT VALUE

AED 412 Million

DURATION

December 2005 to August 2009

LOCATION

Dubai

THE CHALLENGE

Every infrastructure project planned in the middle of an active city is poised to encounter and mitigate various risks, mostly in relation to existing underground utilities. The Dubai Metro project was not an exception. The detection, protection and eventually the diversion of existing utilities was a challenging and critical task for NBHH especially where the underground metro stations, cut and cover tunnels, or piling foundations had to be constructed. The latter construction activities had to be carried out while minimizing the disturbance to the end users and Dubai residents. In that respect, our company managed to overcome all the different challenges, whether foreseen or unforeseen, for a project duration that spanned for three and half years.

SCOPE OF WORK
  • 001Obtaining No Objection Certificates (NOC) from the relevant government departments
  • 002Preparation of shop drawings and method statements
  • 003Trial pits, often by hand digging for initial identification and inspection
  • 004Temporary works such as shoring for deep excavation, dewatering, saw cutting of asphalt
  • 005Reinstatement of roads and pavements
  • 006Supply of all materials and provision of all necessary equipment
  • 007Relocation and protection of existing underground pipes of diameters from 100 mm to 1400 mm for various kind of utilities such as water, sewerage, stormwater drainage, irrigation etc… Including construction of manholes, chambers and connection to existing networks
  • 008Relocation and protection of existing underground cables and ducts for electricity (ADWEA) and telecommunication (Etisalat)
  • 009Micro tunneling and directional drilling for underground crossings and the installation of cables, ducts and pipes
THE FOUNDATION

Committed to excellence in every kilometer, every structure.

Nael & Bin Harmal Hydroexport — architect of the UAE's evolving horizon since 1991.

ABU DHABI

Phone : +971 2 6273344
Fax no. : +971 2 6271165
Location : 6th Floor, Unit 601, Nael & Bin Harmal (NBH) Tower, Zayed The First St. Al Khalidiyah, Abu Dhabi UAE
PO Box : 28102

DUBAI

Phone : +971 4 3599940
Fax no. : +971 4 3599941
Location : 206, Building No: 6 Bay Square, Business Bay, Dubai UAE
PO Box : 29703

© 2026 Nael & Bin Harmal Hydroexport LLC. All rights reserved.