DS-204/C1 Connecting Developed Communities in Dubai Land to DM Sewerage System
CLIENT
Dubai Municipality
CONSULTANT
Khatib & Alami
CONTRACT VALUE
AED 479 Million
DURATION
August 03, 2026 to January 18, 2029
LOCATION
Dubai
THE CHALLENGE
Live roads - Maintain traffic flow and property access during pipeline installation. Ongoing projects - Coordinate work areas, access, and construction sequencing with other contractors. Existing services - Verify utility locations and protect existing services during excavation and NDRC works.
SCOPE OF WORK
- 001Construct 9.67 km of sewerage pipelines, including 2.30 km by open-cut excavation with 12 manholes and 7.37 km by Non-Disruptive Road Crossing (NDRC) with 56 manholes.
- 002Construct 18.10 km of stormwater drainage pipelines, including 7.63 km by open-cut excavation with 39 manholes and 10.47 km by NDRC with 69 manholes.
- 003Install 2.90 km of gully and catch basin connection pipelines, including 140 gullies and catch basins in total.
- 004Construct one sewage pumping station, including civil, mechanical, electrical, and associated works.
- 005Install approximately 838 m of pressure pipeline associated with the sewage pumping station.
- 006Construct approximately 2.73 km of drainage channels.