WATER SUPPLY – WESTERN REGION

Contract G1095

Client : ADWEA
Consultant : Mott Mc Donald
Value : AED 23.4 Million
Duration : June 2002 – June 2003
Location : Abu Dhabi

 

THE CHALLENGE

Contract G1095 covers the construction of reservoirs, tanks, pipes networks and other related works for the supply of water within the western region in Abu Dhabi.

 

SCOPE OF WORKS

• Design and construction of two steel tanks 1 MIG capacity each in Sir Bani Yas Island. The scope includes:
– Topographical and services location survey at site
– Cathodic protection system
– Refurbishment of existing pump station
– Installation of related pipes and miscellaneous civil structures such as valve chambers

• Construction of Water Supply Works at Tarif, Rhadeem and Dhaiyah.
The scope includes:
– Topographic and services location survey
– Demolition of existing structures
– Design and construction of 1 MIG capacity reservoir
– Design and construction of two pumping stations
– All electromechanical and instrumentation works
– Pipes distribution network, connections and valve chambers
– Design and construction of an office and accommodation building for the staff